May 14th Update

To date we have 

  • Mobilized site office, construction equipment and materials

  • Installed perimeter safety fencing, signage, and safety controls

  • Disconnected and removed existing services

  • Commenced interior demolition

  • Commenced heritage restoration work

Next week (week of May 18, 2026)

  • Continue with the interior demolition works 

  • Commence Heritage Brick Salvage (exterior)

  • Removal of Heritage front steps off site

  • Demolition of ramp at Heritage building

  • Delivery of a scissor lift

  • Tentative- Commence main demolition of building with large 340 excavator

Working Hours Remain as

  • Monday to Friday: 7:00am to 7:00pm (per the City Bylaw) however many days will observe 7:00am to 5:00pm

  • Saturday work (as required): 9:00am to 7:00pm

  • No Work on Sunday or Holidays

Health, Safety & Environment

  • The site will be secured at all times

  • The gate closed to the Geneva Center will remain closed at all times, except when deliveries are occurring

  • Dust suppression and noise control measures are being implemented

  • All work will comply with the local regulation and safety standards

Traffic & Access

  • Pedestrian routes will be maintained

  • Traffic control personal and signage will be in place

Contact Information

    Email:  140merton.info@ellisdon.com

    Phone: 416-594-2161

Thank you