May 25th Update

To date we have 

  • Mobilized site office, construction equipment and materials

  • Installed perimeter safety fencing, signage, and safety controls

  • Disconnected and removed existing services

  • Commenced interior demolition

  • Commenced heritage restoration work

Next week

  • Continue with the interior demolition works 

  • Continue with the Heritage Brick Salvage (exterior)

  • Demolition of ramp at Heritage building

  • Delivery of a structural steel for Interior Bracing  - Monday May 25, 2026 

  • Installation of Structural Steel at Heritage building interior

  • Tentative- Exterior works within our property to prepare for Temporary Power, ie. Excavation and cutting of asphalt

  • Tentative - Commence Main demolition of building with large 340 excavator 

  • A few of the above activities, ie. Ramp removal & Brick Salvage removal process will generate loud continuous noise

Working Hours Remain as

  • Monday to Friday: 7:00am to 7:00pm (per the City Bylaw) however many days will observe 7:00am to 5:00pm

  • Saturday work (as required): 9:00am to 7:00pm

  • No Work on Sunday or Holidays

Health, Safety & Environment

  • The site will be secured at all times

  • The gate closed to the Geneva Center will remain closed at all times, except when deliveries are occurring

  • Dust suppression and noise control measures are being implemented

  • All work will comply with the local regulation and safety standards

Traffic & Access

  • Pedestrian routes will be maintained

  • Traffic control personal and signage will be in place

Contact Information

    Email:  140merton.info@ellisdon.com

    Phone: 416-594-2161

Thank you

140 Merton Street Development