May 25th Update
To date we have
Mobilized site office, construction equipment and materials
Installed perimeter safety fencing, signage, and safety controls
Disconnected and removed existing services
Commenced interior demolition
Commenced heritage restoration work
Next week
Continue with the interior demolition works
Continue with the Heritage Brick Salvage (exterior)
Demolition of ramp at Heritage building
Delivery of a structural steel for Interior Bracing - Monday May 25, 2026
Installation of Structural Steel at Heritage building interior
Tentative- Exterior works within our property to prepare for Temporary Power, ie. Excavation and cutting of asphalt
Tentative - Commence Main demolition of building with large 340 excavator
A few of the above activities, ie. Ramp removal & Brick Salvage removal process will generate loud continuous noise
Working Hours Remain as
Monday to Friday: 7:00am to 7:00pm (per the City Bylaw) however many days will observe 7:00am to 5:00pm
Saturday work (as required): 9:00am to 7:00pm
No Work on Sunday or Holidays
Health, Safety & Environment
The site will be secured at all times
The gate closed to the Geneva Center will remain closed at all times, except when deliveries are occurring
Dust suppression and noise control measures are being implemented
All work will comply with the local regulation and safety standards
Traffic & Access
Pedestrian routes will be maintained
Traffic control personal and signage will be in place
Contact Information
Email: 140merton.info@ellisdon.com
Phone: 416-594-2161
Thank you
140 Merton Street Development